Project Diary... Last updated 6th June 2004 |
For sale
6th June 2004 - Time to move on, we're busy planning our next
project, so this one is available for purchase.
The video
Sometime before completion.
The shell
9th May 2000 - yes, that's what it means by
"shell condition". One large concrete space.
The plan
This is how it's going to be....
Let's go
outside
This is what the building looks like from outside. It
used to be a clothing factory.
The lobby
22nd June 2000 - the
existing lobby has been taken down and the framework for the cupboards that
will form the new lobby are put up...
The walls
27th June 2000 - the first walls go up, boarded on one
side only so the services can be put in from the other side.
More walls
28th June 2000 - the tracks for the rest of the walls go
up.
Window
detail
7th July 2000 - the detail around the windows has been
completed. Since the state of our particular concrete beams is the crap side
of urban chic we decided to box them away and go for the clean lines look...
Water
and gas
28th July 2000 - the water and gas mains now go to the service cupboard. This involved nibbling a little chase in the floor
so that there was room for them under the sub floor...
The
rest of the rooms
16th August 2000 - the rest of the two bathrooms and the hall
have now taken shape.
Storage,
storage, storage!
16th August 2000 - if you're going for that clean lines,
modern look then you cant have clutter... We decided to build a loft or two
to give us somewhere to keep those suit cases...
Finally
finialised the kitchen plan
20th August - the kitchen has always been roughly like
this, but the devil is in the details. Things are pretty much decided now
though.
Heat,
Power, Air-con...
22nd September 2000 - the radiators have finally
arrived, the power, lighting and network cables were going in and the first
air-conditioner had been fitted...
The
first hole
3rd October 2000 - we spent 3 months negotiating for the permission to drill
some holes in the external walls. The first hole was drilled on 3rd October.
This one is for the ventilation from the bathrooms.
Finishing
the storage
3rd October 2000 - the door frames and walls around the storage areas are
completed.
Ceilings
11th October 2000 - the remaining ceilings are going up.
Floors
11th October 2000 - almost half of the sub-floors are now down.
Fixings
the radiators
17th October 2000 - the three radiators in the lounge area have were hung on
the 19th October. Before this could be done the walls needed finishing off
and blocks needed to be set up for the radiator bracket fixings.
The
second and third holes
23rd October 2000 -These holes were drilled on the 18th and
23rd October.
Only one more to drill.
Kitchen
extraction
24th October 2000 -The vent for the kitchen extractor, and the external
motor box have now been installed.
Gas to
the hob
27th October 2000 -The gas hob is in the middle of the kitchen area. We
needed to get a gas supply to it.
Pipes
2nd November 2000 - the pipe-work from the (currently non-existent) service cupboard goes in.
Wires
2nd November 2000 - the wiring goes in to the
kitchen walls, and then it's covered up and hidden...
The
service cupboard
17th November 2000 - the framework is created for the
cupboard that will house the boiler, hot water cylinder and all the
air-conditioning stuff.
Beams
20th November 2000 - our concrete beams were enlarged and
used as ducts for the services.
Change of plan
24th November 2000 - as the kitchen units finally start
to go in we realise that the kitchen plan could be tweaked a little.
The
kitchen goes in
24th November 2000 - the kitchen units go in, so that
they can come out, and then go in again, and then...
The
final hole
6th December 2000 - our fourth hole in the wall is
drilled. This one is for the boiler flue.
Services
in the cupboard
8th December 2000 - the condenser units for the
air-conditioning, the cylinder and the boiler are finally fitted in the
service cupboard.
Bathrooms
17th January 2001 - The bathrooms start to be put
together.
Installation
of Worktops
18th January 2001 - The granite worktops are finally
installed in the kitchen. Just the doors, panels and tiling to go...
Power
complete
25th February
2001 - The electrical services
are now complete.
Fireproofing
the lobby
9th March 2001 - Any holes passing through
the walls of the lobby need to be sealed with fireproof mastic...
The
last ceiling
9th March 2001 - Finally,
the last ceiling goes up.
Services
completed
14th March
2001 - The services are now
complete. Central heating, hot water, water softener and air conditioning have
all been commissioned and tested.
Kitchen
doors
28th March
2001 - The kitchen doors are fitted. The stainless steel bar handles are
still to be fitted.
Fancy
stuff
13th April
2001 - The "hot spring"
radiator has now been fitted and the glass brick walls between the bedroom and
the bathrooms have been built.
Preparing
Bathroom 2
27th April 2001 - The walls in the bathroom are prepared
for tiling.
Tiling
Bathroom 2
24th May 2001 - The tiling in bathroom 2 is now complete.
Preparing
Bathroom 1
3rd June 2001 - The walls in the main bathroom are
prepared for tiling.
Tiling
Bathroom 1
16th June 2001 - Tiling in bathroom 1 is 60% complete.
Finishing
Bathroom 1
9th July 2001 - Tiles are grouted, floor's down and the
shower enclosure is fitted.
Lights
15th July 2001 - Lights are put up and then some are
taken down again so that we can paint.
Bathroom
2 floor
15th July 2001 - The remaining area of floor for bathroom
2 is cut to size, it wont actually be laid until the wood floor has been put
down.
All
white
22nd July 2001 - Painting begins.
Almost
white
11th August 2001 - A repaint with a more subtle white.
Extraction
11th August 2001 - The extractor in the kitchen goes up,
comes down and then goes up for good.
Island
Steel
26th August 2001 - The island unit in the kitchen is clad
with stainless steel.
Paint
shop
26th August 2001 - We've set aside one of the rooms to
spray the doors.
Doors
23rd September 2001 - Who would have thought that doors
could take so long to paint...
Time
passes...
6th October 2001 - After the doors were painted we had to
spray the skirting boards and architraves but that's just too boring
to show. Whilst this stuff was being done some finishing touches were being
applied to other rooms.
A
study in white
6th October 2001 - The paint
shop is taken apart, the study walls prepared for painting and the first
coat of obliterating white is applied.
Yellow
peril
23rd October 2001 - This is not the yellow you're looking
for, move along now.
Bedroom
complete
27th October 2001 - The bedroom is complete!
Study
complete
27th October 2001 - The study is complete!
The
last lights
27th October 2001 - All the lights are now up.
Handles
31st October 2001 - Handles are fitted to the wardrobes
and cupboards.
Underlay
2nd November 2001 - The sound-proofing underlay is laid
in the lounge..
Oak
Floor
4th November 2001 - The oak floor starts to go down.
Some
more floor
7th November 2001 - After a day off to let our knees
recover, the floor continues.
A
few blinds
7th November 2001 - We ordered the blinds months ago, and
then wouldn't let them fit them because we weren't
ready...
Lounge
floor complete
12th November 2001 - The lounge floor is now complete,
floor laying moves out into the hall...
Kitchen
floor set-out
17th November 2001 - The tiles for the kitchen floor are
laid out so that the tiles that need cutting can be cut.
Grouting
limestone
21st November 2001 - Grouting of the limestone in the
en-suite bathroom finally begins.
Hall
floor
24th November 2001 - The hall floor is completed and
all the doors are re-hung.
Bedroom
floor
27th November 2001 - The bedroom floor is completed and
the skirting boards begin to be fitted.
Kitchen
handles
30th November 2001 - The kitchen handles are fitted. We
decided against bar handles and went for something a little more
interesting.
We worked like mad to get in before Christmas and moved in on the 13th of December.
A Leak...
15th December 2001 - On the evening of the 14th the
central heating system depressurised and shut down due. The system then
refused to stay at its working pressure. We had a leak. The probable
location of the failure was determined and we cut up the floor to fix it...
Nightmare...
Architraves
and skirting boards
18th January 2002 - The architraves and skirting boards
were sprayed at the same time as the doors. They've now been cut to length
and fitted.
All
done?
18th January 2002 - Things are pretty much complete
now...
25 Beautiful Homes (March 2003 edition)
10th May 2003 - Photos of the flat appear in the magazine
25 Beautiful Homes.
Art
18th August 2003 - We commission
Catherine Purves to produce
some art for us.
For sale
6th June 2004 - Time to move on, we're busy planning our next
project, so this one is available for purchase.
![]() |
Copyright (c) 2000 - 2004 - L. F. Holgate |